Planning: Production Schedule

Pre-production

1. Storyboard - 2 hours
2. Scripting - 2 hours
3. Location recce - 1 day
4. Photo stills - 1 day
5. Health & safety - 1 hour
6. Actor/shot list - 1 hour
7. Equipment list - 1 hour
8. Make-up planning - 1/2 hour
9. Costume planning - 1 hour
10. Logistics - 1/2 hour

Production

1. Script/production run-through - 1/2 hour
2. Weather - constant updates
3. Transport - 5-10 minute journeys
4. Lighting - 1/2 hour
5. Costume/props - 1 hour
6. Filming - 2-4 days

Post-production

1. Editing - 3 days
2. Transitions/titles - 2 days
3. Music/soundtrack - 2 days